Generation Outage Details
Report for Date 20-09-2018 Date of Reporting 21-09-2018
A. Planned Outages
S.NoStationStateAgencyUnit NoCapacity (MW)Reason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1RKM PowerChhattisgarhRKMPPL1360NO SCHEDULE/NO PPA12-07-201816:00-
2CGPLGujaratCGPL_UMPP20830COH & BOTTOM HOPPER SEAL DAMAGED20-09-201800:02-
3DGENGujaratTorrent Power53400NO SCHEDULE(NO PPA)23-12-201619:12-
4DGENGujaratTorrent Power52400NO SCHEDULE(NO PPA)25-11-201620:00-
5SSP RBPH(Hy)GujaratSSP2200Low reservoir level30-06-201723:45-
6SSP RBPH(Hy)GujaratSSP1200Low reservoir level01-07-201700:00-
7SSP RBPH(Hy)GujaratSSP3200Low reservoir level30-06-201723:45-
8SSP RBPH(Hy)GujaratSSP4200Low reservoir level01-07-201700:15-
9SSP RBPH(Hy)GujaratSSP5200Low reservoir level; unit-5 is on AOH since 09:00hrs/01.12.201701-07-201700:30-
10DGENGujaratTorrent Power51400NO SCHEDULE(NO PPA)22-05-201800:00-
11Gandhar GT 3GujaratNTPC3144.30RSD/Changeover for Equalizing Operating hours15-09-201812:31-
12Gandhar GT 2GujaratNTPC2144.30RSD/DUE TO LESS SCHEDULE ON OPEN CYCLE09-09-201800:57-
13SSP RBPH(Hy)GujaratSSP6200Low reservoir level01-07-201700:45-
14GadarwadaMadhya PradeshNTPC1800Unit withdrawn after Testing.04-09-201823:17-
15SasanMadhya PradeshSASAN_UMPP1660AOH17-09-201802:13-
16VSTPSMadhya PradeshNTPC2210AOH05-09-201800:27-
17RGPPLMaharashtraRGPPL1B320Kept on Dry Preservation/gas shortage31-03-201423:00-
18RGPPLMaharashtraRGPPL3A332unit change over;less gas availability07-09-201814:54-
19RGPPLMaharashtraRGPPL3B332 unit change over;less gas availability08-09-201812:14-
20TAPSMaharashtraNPCIL2160REFUELLING OUTAGE.31-07-201821:09-
21RGPPLMaharashtraRGPPL1A320Kept on Dry Preservation/gas shortage08-07-201413:30-
 Sub Total(CS)  7012.60 
  State Sector (SS)
1UNOSUGENGujaratTorrent Power1382RSD04-03-201621:55-
2GSEGGujaratGSECL178RSD18-09-201800:11-
3DGBPGujaratGSECL3375RSD19-09-201801:46-
4UTRAN STG IIGujaratGSECL1375RSD20-09-201822:10-
5GSEG STAGE IIGujaratGSECL1351RSD17-09-201823:39-
6GPPCGujaratGSECL1351RSD.18-09-201811:08-
7GPECGujaratGSECL2218RSD15-09-201821:45-
8KLTPSGujaratGSECL375AOH14-09-201823:58-
9GandhinagarGujaratGSECL5210AOH25-08-201811:48-
10GIPCL STGGujaratGSECL2165No purchase from 1st March 1801-03-201800:00-
11GPECGujaratGSECL1218RSD17-09-201823:24-
12GSEGGujaratGSECL278RSD17-09-201823:54-
13DGBPGujaratGSECL2112RSD17-09-201823:55-
14Sanjay Gandhi TPSMadhya PradeshMPPGCL3210AOH08-09-201819:15-
15TrombayMaharashtraMAHAGENCO6500Unit 6 is kept under economic shutdown since 4th May. 04-05-201600:00-
16PARLIMaharashtraMAHAGENCO4210ECONOMIC SHUT DOWN SINCE 1ST APRIL 201605-07-201518:45-
17PARLIMaharashtraMAHAGENCO5210ECONOMIC SHUT DOWN SINCE 1ST APRIL 201606-07-201514:55-
18PIONEER(262+127)MaharashtraMAHAGENCO1388RSD07-02-201717:45-
19APML TirodaMaharashtraAdani Transmission India Limited3660COH03-09-201805:02-
20WPCLMaharashtraMAHAGENCO1135RSD/No PPA16-02-201617:03-
21WPCLMaharashtraMAHAGENCO2135RSD/No PPA29-02-201621:46-
22URAN B0MaharashtraMAHAGENCO1120Transformer shifting work08-09-201812:19-
 Sub Total(SS) 5556 
Total Planned Outage (CS+SS): 12568.60

B. Forced Outages
S.NoStationStateAgencyUnit NoCapacity(MW)Reason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1BALCO(300 MW)ChhattisgarhBALCO1300Low coal stock05-09-201822:57-
2JPL Stg-IIChhattisgarhJindal power3600Due to increase in H2 of GT-Y phase17-09-201814:00-
3KWPCLChhattisgarhKWPCL1600Stator earth fault protection operated/maintenance22-05-201722:12-
4JPL Stg-IChhattisgarhJindal power1250BTL/coal shortage since 00:00hrs of 03-08-201827-07-201818:40-
5JPL Stg-IIChhattisgarhJindal power4600coal feeding problem (wet coal)/Coal shortage w.e.f 11-09-201808-09-201800:18-
6SKS PowerChhattisgarhSKS2300heavy leakage in feed water control station22-08-201817:20-
7GMR CHHATISGARHChhattisgarhGMR Chattisgarh Energy Ltd2685Turbine casing drain heavy leakage17-04-201823:39-
8JPL Stg-IChhattisgarhJindal power2250Condenser tube leakage/Coal shortage since 00:00hrs of 02-09-201830-08-201821:15-
9NSPCLChhattisgarhNSPCL2250Coal Shortage19-09-201808:45-
10KSKChhattisgarhKSK Mahanadi Power Co Ltd3600ASH EVACUATION SYSTEM PROBLEM;COAL SHORTAGE since 06-07-201805-06-201823:57-
11VandanaChhattisgarhVandana1135BTL09-01-201515:00-
12JPL Stg-IIChhattisgarhJindal power1600hydrogen leakage in generator12-08-201822:30-
13TRN EnergyChhattisgarhACBIL2300PA Hot duct expansion bellow heavy leakage20-09-201800:01-
14GandharGujaratNTPC4224.29Rotor E/F31-08-201822:11-
15CGPLGujaratCGPL_UMPP50830Withdrawn for feed water pre-heater repair15-03-201801:39-
16KAPSGujaratNPCIL2220NUCLEAR REACTOR SIDE PROB01-07-201514:0901-12-2018
17KAPSGujaratNPCIL1220REACTOR SIDE PROBLEM11-03-201608:5201-10-2018
18MB PowerMadhya PradeshMPPGCL2600flame failure17-09-201806:34-
19Dhariwal CTUMaharashtraDhariwal Infrastructure Ltd2300Coal shortage17-09-201800:00-
20Solapur STPSMaharashtraNTPC1660BTL19-09-201805:48-
21GMR WARORAMaharashtraGMR WARORA2300Coal Shortage29-08-201806:12-
 Sub Total(CS) 8824.29 
  State Sector (SS)
1KORBA(E)ChhattisgarhCSPGCL450Due to outage of mill14-09-201815:46-
2KORBA(E)ChhattisgarhCSPGCL150WATER WALL TUBE LEAKAGE06-08-201721:46-
3KORBA(E)ChhattisgarhCSPGCL350Super heater problem12-09-201812:42-
4KORBA(E)ChhattisgarhCSPGCL5120Condenser tube lekage20-09-201822:00-
5KORBA(E)ChhattisgarhCSPGCL250Mill fan problem23-10-201720:53-
6KLTPSGujaratGSECL270Non availability of sufficient coal.11-09-201811:58-
7GPPCGujaratGSECL2351Vaccuum problem17-09-201808:18-
8BECLGujaratGSECL1250Lignite shortage02-07-201811:07-
9BECLGujaratGSECL2250OEM BHEL pending work; UNIT IS OUT DUE TO LIGNITE SHORTAGE AND ALSO WATER SHORTAGE AS INTIMATED BY GUJARAT ON 29-05-201822-04-201800:00-
10EPGLGujaratESSAR2600coal shortage 24-10-201720:25-
11EPGLGujaratESSAR1600Coal shortage23-01-201818:51-
12JP BinaMadhya PradeshMPPGCL2250COAL SHORTAGE20-09-201800:39-
13Sanjay Gandhi TPSMadhya PradeshMPPGCL2210Turbine HP shaft vibration high.20-09-201822:59-
14IEPLMaharashtraIEPL1270Coal Shortage28-08-201821:26-
15UranMaharashtraMAHAGENCO8108heat rate high08-09-201822:08-
16KORADI-2(MSEDCL)MaharashtraMAHAGENCO9660BTL04-09-201812:48-
17KhaparkhedaMaharashtraMAHAGENCO1210Coal Shortage11-08-201823:57-
18KoradiMaharashtraMAHAGENCO6210COAL QUALITY PROBLEM09-09-201805:52-
19Dhariwal STUMaharashtraDhariwal Infrastructure Ltd1300 COAL QUALITY PROBLEM24-08-201814:01-
20GHATGHARMaharashtraMAHAGENCO2125STATOR EARTH FAULT29-06-201801:12-
21RATTAN INDIA POWER(A)MaharashtraRattan India Power Ltd4270Coal Shortage20-09-201800:01-
22NasikMaharashtraMAHAGENCO5210Due to CLG tower 5A HDR leakage.11-09-201818:45-
23ParasMaharashtraMAHAGENCO3250GT PROTECTION OPERATED.15-09-201800:55-
24PARLIMaharashtraMAHAGENCO6250due to critical coal bunker level 12-09-201806:57-
25ChandrapurMaharashtraMAHAGENCO6500Clinker removal14-09-201823:57-
26KoradiMaharashtraMAHAGENCO7210Coal Shortage03-08-201815:54-
27UranMaharashtraMAHAGENCO7108Compressor search protection20-07-201812:53-
28BhusawalMaharashtraMAHAGENCO3210COAL SHORTAGE07-06-201800:02-
29KhaparkhedaMaharashtraMAHAGENCO2210BTL10-09-201802:35-
 Sub Total(SS)7002 
Total Forced Outage (CS+SS): 15826.29

Regional Generation Outage Summary (MW)
Central SectorState SectorRegional Total Outage(MW)
PlannedForcedTotal(CS)PlannedForcedTotal(SS)
7012.608824.2915836.89555670021255828394.89

Generating Units Revived during last day which were out before 20-09-18
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageRevival
DateTimeDateTime
  Central Sector (CS)
--No Outages--
 Sub Total(CS) 0 
  State Sector (SS)
1Satpura IVMadhya PradeshMadhya Pradesh11250tripped while testing of PSS tuning17-09-201815:3920-09-201801:05
2UTRAN STG IIGujaratGujarat1375RSD.19-09-201809:0620-09-201811:28
3KORBA EAST EXT(DSPM)ChhattisgarhChattisgarh2250BTL.19-09-201809:5020-09-201822:30
4GPECGujaratGujarat3218RSD19-09-201823:5420-09-201811:11
 Sub Total(SS) 1093 
Total (CS+SS): 1093

Outages due to Low Demand
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1DGENGujaratTorrent Power52400NO SCHEDULE(NO PPA)25-11-201620:00-
2DGENGujaratTorrent Power53400NO SCHEDULE(NO PPA)23-12-201619:12-
3DGENGujaratTorrent Power51400NO SCHEDULE(NO PPA)22-05-201800:00-
4RKM PowerChhattisgarhRKMPPL1360NO SCHEDULE/NO PPA12-07-201816:00-
5Gandhar GT 2GujaratNTPC2144.30RSD/DUE TO LESS SCHEDULE ON OPEN CYCLE09-09-201800:57-
6Gandhar GT 3GujaratNTPC3144.30RSD/Changeover for Equalizing Operating hours15-09-201812:31-
 Sub Total(CS) 1848.60 
  State Sector (SS)
1WPCLMaharashtraMaharashtra1135RSD/No PPA16-02-201617:03-
2WPCLMaharashtraMaharashtra2135RSD/No PPA29-02-201621:46-
3UNOSUGENGujaratTorrent Power1382RSD04-03-201621:55-
4PIONEER(262+127)MaharashtraMaharashtra1388RSD07-02-201717:45-
5GPECGujaratGujarat2218RSD15-09-201821:45-
6GPECGujaratGujarat1218RSD17-09-201823:24-
7GSEG STAGE IIGujaratGujarat1351RSD17-09-201823:39-
8GSEGGujaratGujarat278RSD17-09-201823:54-
9DGBPGujaratGujarat2112RSD17-09-201823:55-
10GSEGGujaratGujarat178RSD18-09-201800:11-
11GPPCGujaratGujarat1351RSD.18-09-201811:08-
12DGBPGujaratGujarat3375RSD19-09-201801:46-
13UTRAN STG IIGujaratGujarat1375RSD20-09-201822:10-
 Sub Total(S S) 3196 
Total Low Demand Outage (CS+SS): 5044.60