Generation Outage Details
Report for Date 23-06-2019 Date of Reporting 24-06-2019
A. Planned Outages
S.NoStationStateAgencyUnit NoCapacity (MW)Reason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1RKM PowerChhattisgarhRKMPPL4360Commercial operation declared from 00:00hrs of 20-03-2019; kept out on less fuel; intimated that from 10-05-2019, the reason is no schedule due to no PPA20-03-201900:00-
2GMR CHHATISGARHChhattisgarhGMR Chattisgarh Energy Ltd1685Coal shortage22-06-201906:11-
3RKM PowerChhattisgarhRKMPPL3360tripped on bearing problem in ID fan; reason changed as No schedule due to no PPA since 00:00hrs/10-05-201908-05-201921:30-
4SSP RBPH(Hy)GujaratSSP4200Low reservoir level01-07-201700:15-
5KawasGujaratNTPCGT 1A106RSD21-06-201921:11-
6Gandhar GT 3GujaratNTPC3144.30C-inspection(Major Overhauling)14-06-201900:00-
7CGPLGujaratCGPL_UMPP40830for generator inspection & capital overhauling15-06-201901:17-
8Gandhar GT 1GujaratNTPC1144.30RSD20-06-201906:04-
9KawasGujaratNTPCGT 1B106RSD21-06-201900:10-
10CGPLGujaratCGPL_UMPP50830COH15-06-201908:45-
11KawasGujaratNTPCST 1C116.10RSD21-06-201921:05-
12DGENGujaratTorrent Power53400RSD01-05-201900:40-
13DGENGujaratTorrent Power52400RSD01-05-201900:05-
14SSP RBPH(Hy)GujaratSSP6200Low reservoir level01-07-201700:45-
15SSP RBPH(Hy)GujaratSSP3200Low reservoir level30-06-201723:45-
16SSP RBPH(Hy)GujaratSSP1200Low reservoir level01-07-201700:00-
17SSP RBPH(Hy)GujaratSSP5200Low reservoir level; unit-5 is on AOH since 09:00hrs/01.12.201701-07-201700:30-
18SSP RBPH(Hy)GujaratSSP2200Low reservoir level30-06-201723:45-
19RGPPLMaharashtraRGPPL1B320Kept on Dry Preservation/gas shortage31-03-201423:00-
20Solapur STPSMaharashtraNTPC2660RSD13-06-201923:30-
21RGPPLMaharashtraRGPPL2A332unit change over; less gas fuel18-04-201900:03-
22RGPPLMaharashtraRGPPL2B332unit change over; less gas fuel15-04-201918:30-
23RGPPLMaharashtraRGPPL1A320Kept on Dry Preservation/gas shortage08-07-201413:30-
24Solapur STPSMaharashtraNTPC1660RSD16-06-201901:21-
 Sub Total(CS)  8305.70 
  State Sector (SS)
1DGBPGujaratGSECL3375RSD.12-06-201915:42-
2GIPCL STGGujaratGSECL2165No purchase from 1st March 1801-03-201800:00-
3GPEC GTGujaratTorrent Power3138No schedule(PPA expired)10-12-201811:36-
4GPEC GTGujaratTorrent Power1138No schedule(PPA expired)10-12-201812:34-
5GPEC GTGujaratTorrent Power2138No schedule(PPA expired)10-12-201818:55-
6GPPCGujaratGSPC2351RSD17-10-201820:47-
7GSEGGujaratGSPC178RSD11-10-201822:26-
8GandhinagarGujaratGSECL4210RSD12-06-201921:41-
9GandhinagarGujaratGSECL3210RSD.12-06-201919:49-
10UTRAN STG IIGujaratGSECL1375RSD22-06-201916:28-
11Satpura IVMadhya PradeshMPPGCL10250Tripped on Abnormal noise on 02-05-2019; converted to AOH since 00:00hrs of 11-05-2019 for 25days.02-05-201914:34-
12SingajiMadhya PradeshMPPGCL1600COH05-06-201923:49-
13PIONEER(262+127)MaharashtraMAHAGENCO1388RSD07-02-201717:45-
14PARLIMaharashtraMAHAGENCO4210ECONOMIC SHUT DOWN SINCE 1ST APRIL 201605-07-201518:45-
15PARLIMaharashtraMAHAGENCO8250No schedule04-06-201900:00-
16PARLIMaharashtraMAHAGENCO6250RSD12-12-201800:00-
17URAN B0MaharashtraMAHAGENCO1120Transformer shifting work08-09-201812:19-
18WPCLMaharashtraMAHAGENCO3135AOH01-11-201800:28-
19APML TirodaMaharashtraAdani Transmission India Limited4660tripped on MS drain bonnet leakage; converted to AOH for 35days w.e.f. 11:55hrs/20-06-201919-06-201916:09-
20WPCLMaharashtraMAHAGENCO4135RSD15-12-201800:00-
21TrombayMaharashtraMAHAGENCO6500Unit 6 is kept under economic shutdown since 4th May. 04-05-201600:00-
22WPCLMaharashtraMAHAGENCO2135RSD27-11-201800:00-
23PARLIMaharashtraMAHAGENCO5210ECONOMIC SHUT DOWN SINCE 1ST APRIL 201606-07-201514:55-
24RATTAN INDIA POWER(A)MaharashtraRattan India Power Ltd1270Zero schedule14-06-201900:01-
 Sub Total(SS) 6291 
Total Planned Outage (CS+SS): 14596.70

B. Forced Outages
S.NoStationStateAgencyUnit NoCapacity(MW)Reason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1JPL Stg-IIChhattisgarhJindal power3600leakage in Super Heater spray line./coal shortage wef 00:00hrs/02-06-201927-05-201902:14-
2KWPCLChhattisgarhKWPCL1600Stator earth fault protection operated/maintenance22-05-201722:12-
3JPL Stg-IIChhattisgarhJindal power1600Condenser tube leakage./coal shortage16-03-201902:07-
4BALCOChhattisgarhBALCO4135Turbine problem20-06-201922:56-
5Essar(Mahan)ChhattisgarhESSAR1600APH issue 22-06-201915:55-
6Korba STPSChhattisgarhNTPC1200Drum level low./internal circuit leakages17-06-201914:45-
7VandanaChhattisgarhVandana1135BTL09-01-201515:00-
8KSKChhattisgarhKSK Mahanadi Power Co Ltd3600ID fan Problem04-06-201907:17-
9RKM PowerChhattisgarhRKMPPL1360BTL12-05-201914:01-
10JPL Stg-IChhattisgarhJindal power1250Coal shortage24-10-201800:00-
11JPL Stg-IChhattisgarhJindal power2250Condenser tube leakage/Coal shortage since 00:00hrs of 02-09-201830-08-201821:15-
12CGPLGujaratCGPL_UMPP30830BTL18-06-201923:14-
13VSTPSMadhya PradeshNTPC7500GT 7R bushing failure, subsequently impedance protection, turbine overspeed etc 19-05-201910:35-
 Sub Total(CS) 5660 
  State Sector (SS)
1KORBA(E)ChhattisgarhCSPGCL5120Mill fan trip23-06-201902:33-
2KORBA(E)ChhattisgarhCSPGCL450Due to outage of mill14-09-201815:46-
3KORBA(E)ChhattisgarhCSPGCL250Mill fan problem23-10-201720:53-
4KORBA(W) EXTNChhattisgarhCSPGCL5500tripped on Flame failure/kept out to attend various leakages23-06-201900:00-
5KORBA(E)ChhattisgarhCSPGCL150WATER WALL TUBE LEAKAGE06-08-201721:46-
6KORBA(E)ChhattisgarhCSPGCL350Super heater problem12-09-201812:42-
7KORBA(W) CSPGCL ChhattisgarhCSPGCL3210Y Phase jumper broken 24-02-201922:43-
8DGBPGujaratGSECL2112Gas line problem.19-06-201922:30-
9SLPPGujaratGIPCL2125BTL23-06-201911:18-
10KLTPSGujaratGSECL170Non availability of coal.12-06-201915:00-
11OPGSGujaratGSECL1150Station T/F Oil leakage.19-06-201922:47-
12EPGLGujaratESSAR2600coal shortage 24-10-201720:25-
13DGBPGujaratGSECL1107TRIPPED DUE TO TRIPPING OF EVACUATION LINES/LATER TURBINE GEAR PROBLEM DEVELOPED25-09-201812:54-
14GSEGGujaratGSPC278Turbine bearing vibration high 05-10-201819:38-
15GPECGujaratCLPIPL4241High pressure control valve problem06-12-201816:36-
16BECLGujaratGSECL1250Fire in bunker feeding system.29-03-201919:52-
17OPGSGujaratGSECL2150Station T/F oil leakage19-06-201922:47-
18KLTPSGujaratGSECL475BTL22-06-201901:01-
19BECLGujaratGSECL2250PA Fan Damper jammed22-06-201907:06-
20GPPCGujaratGSPC1351non-availability of gas23-05-201919:15-
21SUGENGujaratTorrent Power1382BTL23-06-201900:24-
22Satpura IIIMadhya PradeshMPPGCL9210ID fan problem.19-06-201916:35-
23Satpura IIMadhya PradeshMPPGCL7210Vacuum low29-05-201911:30-
24Sanjay Gandhi TPSMadhya PradeshMPPGCL2210BTL21-06-201914:19-
25Sanjay Gandhi TPSMadhya PradeshMPPGCL1210Furnace pressure very high10-06-201912:57-
26SingajiMadhya PradeshMPPGCL3660ESP hopper problem10-06-201917:54-
27IEPLMaharashtraIEPL1270Coal Shortage28-08-201821:26-
28VIPLMaharashtraMAHAGENCO1300Coal shortage29-12-201800:30-
29PARLIMaharashtraMAHAGENCO7250UNIT BOARD TRIPPED 22-06-201917:48-
30VIPLMaharashtraMAHAGENCO2300COAL SHORTAGE17-01-201900:15-
31WPCLMaharashtraMAHAGENCO1135fLAME fAILURE25-11-201804:48-
32UranMaharashtraMAHAGENCO7108Compressor search protection20-07-201812:53-
33ChandrapurMaharashtraMAHAGENCO7500BTL18-06-201915:41-
34UranMaharashtraMAHAGENCO8108Boiler protection operated 22-06-201915:40-
 Sub Total(SS)7442 
Total Forced Outage (CS+SS): 13102

Regional Generation Outage Summary (MW)
Central SectorState SectorRegional Total Outage(MW)
PlannedForcedTotal(CS)PlannedForcedTotal(SS)
8305.70566013965.70629174421373327698.70

Generating Units Revived during last day which were out before 23-06-19
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageRevival
DateTimeDateTime
  Central Sector (CS)
1TRN EnergyChhattisgarhACBIL2300TURBINE VIBRATION 13-05-201910:1623-06-201915:29
2GandharGujaratNTPC4224.29RSD14-06-201911:4923-06-201900:40
3SasanMadhya PradeshSASAN_UMPP2660BTL22-06-201911:1523-06-201914:10
 Sub Total(CS) 1184.29 
  State Sector (SS)
1ALTPSGujaratGMDC1125Boiler problem12-06-201901:2023-06-201913:39
2GSEG STAGE IIGujaratGSPC1351RSD22-06-201923:3723-06-201915:45
3KoradiMaharashtraMaharashtra7210Auxiliary problem22-06-201923:5023-06-201907:23
 Sub Total(SS) 686 
Total (CS+SS): 1870.29

Outages due to Low Demand
S.NoStationLocationOwnerUnit NoCapacityReason(s)OutageExpected Revival Date
DateTime
  Central Sector (CS)
1RKM PowerChhattisgarhRKMPPL4360Commercial operation declared from 00:00hrs of 20-03-2019; kept out on less fuel; intimated that from 10-05-2019, the reason is no schedule due to no PPA20-03-201900:00-
2DGENGujaratTorrent Power52400RSD01-05-201900:05-
3DGENGujaratTorrent Power53400RSD01-05-201900:40-
4RKM PowerChhattisgarhRKMPPL3360tripped on bearing problem in ID fan; reason changed as No schedule due to no PPA since 00:00hrs/10-05-201908-05-201921:30-
5Solapur STPSMaharashtraNTPC2660RSD13-06-201923:30-
6Solapur STPSMaharashtraNTPC1660RSD16-06-201901:21-
7Gandhar GT 1GujaratNTPC1144.30RSD20-06-201906:04-
8KawasGujaratNTPCGT 1B106RSD21-06-201900:10-
9KawasGujaratNTPCST 1C116.10RSD21-06-201921:05-
10KawasGujaratNTPCGT 1A106RSD21-06-201921:11-
 Sub Total(CS) 3312.40 
  State Sector (SS)
1PIONEER(262+127)MaharashtraMaharashtra1388RSD07-02-201717:45-
2GSEGGujaratGSPC178RSD11-10-201822:26-
3GPPCGujaratGSPC2351RSD17-10-201820:47-
4WPCLMaharashtraMaharashtra2135RSD27-11-201800:00-
5GPEC GTGujaratTorrent Power3138No schedule(PPA expired)10-12-201811:36-
6GPEC GTGujaratTorrent Power1138No schedule(PPA expired)10-12-201812:34-
7GPEC GTGujaratTorrent Power2138No schedule(PPA expired)10-12-201818:55-
8PARLIMaharashtraMaharashtra6250RSD12-12-201800:00-
9WPCLMaharashtraMaharashtra4135RSD15-12-201800:00-
10PARLIMaharashtraMaharashtra8250No schedule04-06-201900:00-
11DGBPGujaratGSECL3375RSD.12-06-201915:42-
12GandhinagarGujaratGujarat3210RSD.12-06-201919:49-
13GandhinagarGujaratGujarat4210RSD12-06-201921:41-
14UTRAN STG IIGujaratGSECL1375RSD22-06-201916:28-
 Sub Total(S S) 3171 
Total Low Demand Outage (CS+SS): 6483.40